REFERENCE PROJECTS – ARCHIVE
Here you can see references from the past months.
ARCHIVE – PROJECTS: CIVIL ENGINEERING & ROAD CONSTRUCTION
CIVIL ENGINEERING & ROAD CONSTRUCTION
RENOVATION OF THE
A96
Total length | 2 x 5,900 m |
Width | 11.5 m |
Junctions | 3 |
Construction period | 03/2019 – 12/2019 |
Customer | Bavaria motorway authority |
Total value of construction project | approx. EUR 10,500,000 |
Junctions | Dual carriageways, with three junctions on each side |
Material excavated from utility trenches | 9,500 m³ |
Prefabricated shafts | 150 units |
Seepage pipes | 5,100 m |
Sewer pipes | 5,100 m |
Milled asphalt layers | 64,000 tonnes |
Milled hydraulically bound bearing layer with tachymeter | 140,000 m² |
Asphalt layers composed of bearing, binding and top layers | approx. 77,000 tonnes |
Creation of road shoulder | 21,000 m |
Collaboration with the world’s largest road paver Vögele
From March to December 2019, KUTTER was commissioned by the Kempten agency of the Bavaria motorway authority to renovate the A96 over a total length of 2x 5,900 m and a width of 11.5 m.
The construction site included three junctions. Collaboration from the start: with the world’s largest road paver Vögele.
We would like to thank Vögele for providing us with the impressive video featuring the road renovation project.
CIVIL ENGINEERING & ROAD CONSTRUCTION
REDESIGN OF
KEMPTEN TOWN PARK
Construction period | 10/2108 - 12/2019 |
Order value | EUR 4,700,000 |
Ductwork for cables | 2,500 m |
Laid cabling | 3,200 m |
Earthworks | 3,000 m³ |
Installation of gravel & paving | 1,800 m³ |
Large granite paving | 3,400 m² |
Edging of meadow area | 500 m |
Built by Kutter!
The town park in Kempten was redesigned in October 2018. KUTTER was involved as the lead construction company. 2,500 m of ductwork for cables were laid with a total of 3,200 m of cabling.
The park has a new paved surface covering a total area of 6,400 m² and consisting of large granite paving from four different quarries. A border of approx. 500 m in length was also created around the meadow area.
In addition, the design of the central bus stops was optimised and permanent installations were also created for the Allgäu Festival Week. Particular highlights also include the fountains with lighting effect and underground water supply shaft.
Our teams made sure the trees were fully protected of course during all the construction work.
We are delighted that the town of Kempten has documented the construction work and made the material available to us.
CIVIL ENGINEERING & ROAD CONSTRUCTION
ALLGÄU AIRPORT
MEMMINGEN
Construction period | 03/2019 until end 10/2019 |
Work | Laying of a ductwork system, widening of the runway |
Order value | EUR 14,000,000 |
Total value of construction project | EUR 22,000,000 |
Other details | EU tender |
TIME FOR THE NIGHT SHIFT
KUTTER beats off EU-wide competition
From a military airport to one of the most important backbones of the Free State of Bavaria: Allgäu Airport in Memmingen has been an important hub for some time now. It offers flights to Egypt, Corsica, Italy, Morocco, Spain, Portugal, Great Britain and many more destinations. With a new record flight plan of over 50 destinations, it is attracting increasing numbers of holidaymakers and business travellers. In order to be able to offer additional, varied destinations to its many air passengers in future, the airport is now being expanded – not least so it can continue to fulfil the increasingly strict international security guidelines.
After a ten-month marathon of negotiations, this challenging and exciting project was awarded to KUTTER. The costing work alone for this EU-wide tender took almost two months. This was followed by a lengthy planning process with regard to employee self-monitoring as well as a time-consuming approval process for each individual worker and each individual machine – after all, the project was for an airport, classed therefore as a high-security zone. Ultimately, KUTTER was able to complete the tender stage to the utmost satisfaction of the customer and emerged successful in face of the competitors from across the EU. Last November, the groundbreaking ceremony for the renovation project took place in the presence of Bavarian Minister President Markus Söder.
The excavators roll onto site at 9.30pm
Since March 2019, it’s been a daily occurrence for the KUTTER team: “Time for the night shift!”. As soon as the last flights have left the runway, the large construction machines start moving. First of all, cable trenches for a ductwork system were dug out along the entire runway, in which the electrics for the runway lighting will be installed at a later point. The biggest challenge: By 6am precisely when the first planes start moving, all the machinery must be returned the garage, and all the holes and trenches must be filled in until the four KUTTER crews get back to work again in the evening at 9.30pm.
Complete closure of the airport in autumn
Things will get really exciting in early autumn, when the airport will be completely closed to air traffic for the last two weeks of September. This is when the work will ramp up and be performed day and night in shifts to extend the width of the runway from 30 to 45 metres across its entire length. It will be a race against time as no delays can be afforded, considering the fact that the largest airline Ryanair will suspend all air traffic during this period.
Financed by the free state
The mammoth project is being partially financed by the Free State of Bavaria as well as the airport’s shareholders. The order value of the civil engineering work performed by KUTTER alone equates to EUR 15 million. To get an overview of the large construction project, Bavarian State Minister for Construction and Transport, Dr Hans Reichert, recently visited the site. Together with the airport’s CEO, Ralf Schmid, and Member of Bavarian State Parliament, Klaus Holetschek, KUTTER CEO, Peter Groll, and Head of Division, Andreas Binder visited the site with the politician, explaining the individual work steps and highlighting the particular challenges for both the workers and the machinery.
KUTTER in the media
Naturally, the project is being covered by the media. The press reports regularly on the progress, as do TV channels such as Allgäu-TV, which is often on site and broadcasts impressive footage of what is currently happening on the construction site.
The renovation works are scheduled to be completed in 2020. Besides expanding the runway and replacing the instrument landing system, the luggage halls are also being extended, the apron areas are being widened and a rainwater retention basin is being built.
KUTTER is proud to play a leading role in shaping such an important, regional project and wishes all of the employees involved every success!
ASPHALT PAVING
ASPHALT PAVING
A96 ROAD RENOVATION
ECHING – WINDACH
Work | asphalt paving |
Asphalt milling | 87,000 m² |
Replacement of road gullies | 280 units |
Renovation of road shoulder | 16,000 m |
Asphalt binding layer | AC 16 BS 19,000 to |
Asphalt top layer | made of PA 8 9,500 to |
Marking work | 30,000 m |
CHALLENGE ON THE A96
Extremely high flows of traffic
Besides the A8, the A96 is an important East-West transport connection in Southern Germany. It connects the arterial roads from Salzburg and Nuremberg via Munich heading towards Austria and Switzerland. Last year, KUTTER completed the renovation of the asphalt surface between Windach and Eching tunnel on the A96. The direction of traffic towards Munich was a particular challenge in the mornings due to heavy volumes of traffic.
The special contractual terms demonstrated how important the motorway is for the smooth flow of traffic. The timetable of just 14 days per direction of traffic was very ambitious. The construction work was carried out while maintaining the flow of traffic. During the day, the traffic was managed using 3 lanes + 1 lane on the construction site side. This meant there were 2 lanes available in each direction of traffic. During this time, the teams worked in operating mode 2: “Daytime construction site making use of daylight”. For work carried out at night (construction of the asphalt layers), the traffic was managed using 3 lanes + 0 lanes on the construction site side, in operating mode 3: “Execution of work at night”. The Kempten agency of the Bavaria motorway authority awarded the contract worth EUR 4.2 million to KUTTER. The planned renovation work included replacing the asphalt binding and top layers over a length of 4.5 km in each direction of traffic. During the planned construction period between July and September, we had just 14 days per direction of traffic to complete the milling and asphalt work (on the night shift). All of this requires precise planning, a great deal of flexibility and expert staff.
Despite the rigid timetable, KUTTER met all deadlines. Work is also planned this year for an additional section of the A96 between Eching tunnel and Etterschlag tunnel. We hope to win this contract too. We have the experience!
ASPHALT PAVING
B17 ROAD RENOVATION
AUGSBURG – HAUNSTETTEN
Milling work | 45,000 m³ |
Asphalt binding layer | AC 16 BS 30,000 m² |
Asphalt top layer | SMA 8 S 30,000 m² |
Entrance and exit ramps | AC 11 DS 15,000 m² |
Milling work | 45,000 m² |
Order value | EUR 1,230,000 |
Extensive milling and asphalt work
Working day and night on the B17
In July 2019, commissioned by the state building authority of Augsburg, KUTTER carried out road renovations on two sections of the B17 between the junctions for Messe and Eichleitnerstrasse.
Working day and night, the milling department successfully completed the work within 20 days. After expanding the upper road shoulder, the milling machines were put to work. This involved removing the damaged areas as well as the subsequent reconstruction of the road shoulder.
Almost EUR 1.25 million of funding was available for the entire construction work.
ARCHIVE – PROJECTS: STRUCTURAL ENGINEERING
STRUCUTRAL ENGINEERING
REDEVELOPMENT OF THE MONASTERY ECONOMY
OTTOBEUREN
Construction period | 01/2022 - 03/2023 |
Customer | Benedictine Abbey Ottobeuren |
Rebar | 104 to |
Reinforced concrete ceilings | 1.239 m² |
Wood-concrete composite ceilings | 875 m² |
Concrete | 1.420 m³ |
Masonry surfaces | 927 m² |
Order value | EUR 1,300,00.00 |
From monastic economy
becomes residential complex
For a little over a year, one of our building construction teams was involved in the renovation of the former monastery economy in Ottobeuren, which will comprise 24 residential units with underground parking and outbuildings after completion.
KUTTER took care of the shell construction and wishes good luck for the further construction project.
PROJECT DEVELOPMENT
THE GULDEIN
MUNICH
Construction period | 10/2020 - 12/2022 |
Land area | 1.182 m² |
Gross floor area | 1.800 m² |
Total living area | 1.434 m² |
Apartments | 21 |
Underground parking spaces | 17 |
of which multiple parkers | 8 |
Barrier-free, urban living
Executed by the KUTTER Munich branch, an urban residential building in the rear building style was created in the sought-after Munich Westend, which offers its residents barrier-free, ultra-modern apartments between 40 and 125 m2 of living space.
KUTTER has succeeded in creating a residential building that makes optimal use of the limited space available in a grown inner city district and combines comfort and energy efficiency with urban charm.
Architecturally, the building is designed in such a way that each apartment has an outdoor space in the form of a balcony or terrace. Away from the street there is also a garden area with a small playground, which gives the residents of the Guldein a private, green oasis. The residential units are supplemented by a cellar compartment, areas that can be used jointly, as well as a washing and drying room and bicycle rooms. A total of 17 underground parking spaces are also available.
To give you a little insight, click here for the online tour.
Strucutral Engineering
Loading and assembly hall
Hawangen
Construction period | 03/2022 - 12/2022 |
Customer | Hans Hundegger AG |
Order value | EUR 1,970,000 |
Earth and reinforced concrete work Industrial hall with office
In March, KUTTER started the contract for the building construction, civil engineering and road construction divisions with the preparatory earthwork for the new loading and assembly hall for Hundegger in Hawangen. The finished building was ready by June and could be handed over to the customer. By the end of the year, all necessary measures will also be completed in the outdoor area.
Thank you for the order and the trust you have placed in us!
Structural Engineering
Seniors residence
Kisslegg
Construction period | 08/2021 - 06/2022 |
Customer | Heim Infrastruktur |
Gross floor area | 5.500 m² |
Order value | EUR 2,613,600 |
Living well even in old age
From August 2021 to June 2022, KUTTER took over the shell construction of the senior citizens' residence in Kissleg.
33 one- to three-room apartments and 60 one-room apartments have been built on the 5,500 m² property. The facility should be ready for occupancy by June 2023.
KUTTER wishes continued good construction progress.
TURNKEY CONSTRUCTION
BUILDING OF A NEW MULTI-FAMILY DWELLING
LINDAU
Construction period | 01/2021 - 03/2022 |
Customer | GWG Lindauer Wohnungsgesellschaft mbH |
Gross floor area | 720 m² |
Order value | EUR 1,100,000 |
Six-family dwelling ready for occupancy
In the border town of Lindau, KUTTER handed over a ready-to-occupy, newly built six-family dwelling to the customer. The construction period was almost 14 months and work was completed according to plan.
TURNKEY CONSTRUCTION
SHOPPING CENTRE
BUXHEIM
Construction period, EDEKA | 04/2019 - 03/2020 |
Construction period, office and commercial building | 07/2020 - 03/2022 |
Customer | NVZ Buxheim GmbH & Co. KG |
Gross floor area: EDEKA | 4,284 m² |
Gross floor area: office and commercial building | 3,997 m² |
Order value | EUR 11,000,000 |
EDEKA, office and commercial building
A large construction project was successfully completed according to schedule in spring.
Buxheim now boasts a modern shopping centre, including an EDEKA supermarket with drinks store and bakery as well as an office and commercial building with underground car park. KUTTER completed the turnkey construction of both buildings.
STRUCTURAL ENGINEERING
DISTRICT HEATING PLANT
RAVENSBURG
Construction period | 03/2021 - 10/2021 |
Customer | District of Ravensburg |
Order value | EUR 526,500 |
Self-sufficiency for the school district
The aim of the new heating plant that was inaugurated in spring by Head of the District Authority, Harald Sievers, is for the area – which will also include a central, district council building and a newly built school – to become self-sufficient in terms of power by 2026.
KUTTER made a huge contribution towards the project with the construction of the heating plant and its eight-metre-high exposed concrete walls. We would like to thank the District of Ravensburg for awarding this contract to us.
PROJECT DEVELOPMENT
KÖNIGSGRABEN
MEMMINGEN
Construction period | 02/2020 - 11/2021 |
Property surface area | 3,100 m² |
Gross floor area | 3,248 m² |
Total living space | 2,822 m² |
Multi-family dwellings | 3 |
Apartments | 28 |
Underground parking spaces | 28 |
Modern and close to the centre
Just a few steps from Memmingen’s old town, KUTTER created a modern residential area as part of a construction project lasting almost two years.
A total of three buildings 28 flats have been created, and each residential unit also has a underground parking space.
High-quality materials, modern floor plans and the latest technical equipment turned the project into a real residential experience.
All the units have already been sold and are currently occupied.
Special feature: the fully automatic parking system
Watch the Video here!
STRUCTURAL ENGINEERING
JOHANNITER DAY NURSERY
MEMMINGEN
Construction period | 04/2021 - 03/2022 |
Customer | Johanniter Unfall Hilfe e.V. |
Property surface area | 4,600 m² |
Order value | EUR 686,755 |
A new day nursery building belonging to Johanniter Unfall Hilfe e.V. is being built on Lisztstrasse in Memmingen
A total of 582 m² distributed across two floors will offer space for 100 children in the future. On both floors, two group rooms each are currently being built, with adjoining rooms and sanitary facilities. On the L-shaped ground floor, there is also a multi-purpose room, staff rooms and a kitchen area. On the eastern single-storey part of the building, a partly paved roof terrace is being built that will be connected to the external premises via a staircase and a slide.
KUTTER will complete the construction work according to schedule in March.
STRUCTURAL ENGINEERING
NEW VITERMA BUILDING
MEMMINGEN
Customer | Viterma Deutschland GmbH |
Construction period | 09/2021 - 02/2022 |
Excavation volume | 5,000 m³ |
Order value | EUR 329,538.64 |
Construction of a new showroom
KUTTER is currently building a new storage hall with offices on Teramostrasse for bathroom fitter Viterma. This will mean even more space for the bathroom showroom.
On a land surface area of 3,000 m², a large building measuring around 680 m² is under construction. Work began at the start of September. The KUTTER team expects the building to be completed by February.
STRUCTURAL ENGINEERING
ROOF CANOPY FOR USED PAPER AREA AT KOLB
KAUFBEUREN
Construction period | 07/2021 - 10/2021 |
Customer | Alwin Kolb GmbH & Co. KG |
Excavation | 2,000 m³ |
Gravel installation | 1,350 m³ |
Asphalt | 2,400 m² |
Order value | EUR 976,000 |
Working during ongoing operation
Over a four-month construction period, KUTTER built a roof canopy for the used paper area in Kaufbeuren. As Kolb did not want to interrupt its work processes, the construction work had to take place during ongoing operation, which was particular challenging. It included, for example, the successful replacement of cable ducting during operation.
PROJECT DEVELOPMENT
ZAUBZERSTRASSE
MUNICH
Construction period | 06/2019 - 08/2021 |
Property surface area | 804 m² |
Gross floor area | 2,713 m² |
Total living space | 1,611.91 m² |
Town houses | 6 |
City apartments | 7 |
Penthouses | 4 |
Underground parking spaces | 22 |
An exclusive location
At a premium location in Bogenhausen, not far from the Maximilianeum, the Prince Regent Theatre and the River Isar, ZAUBZER 29 is place of calm. The neighbourhood is composed of magnificent villas, elegant multi-family dwellings and lots of green space. The proximity to Odeonsplatz, the excellent infrastructure and the Angel of Peace, guardian of the district, underpin the exclusive character of the complex.
Urban living begins with architectural language. ZAUBZER 29 is a contemporary place for communal living. Instead of picking up on the cheerful stucco façades of the neighbourhood, the architect focused on clear, straight shapes and functional aesthetics. Tradition meets modernity.
ZAUBZER 29 stands for spacious living with the best materials and future-proof technology. The residents benefit from energy efficiency, high safety standards and maximum comfort for healthy living. Large windows provide wonderful views of the gardens or the city. From high-quality wooden flooring to exclusive designer tiles, everything has been designed with the best quality in mind.
turnkey construction
New construction of the ABS facility
North West Paderborn
builder | KUTTER GmbH & Co. KG |
Construction period | 05/2019 - 11/2020 |
project volume | EUR 4 Mio. |
land area | 15,010 m² |
NGF | 1,583 m² |
BGF | 1,675 m² |
BRI | 14,477 m³ |
New administration building and workshop
From May 2019 to November 2020, ABS Nord-West GmbH built a new turnkey facility in Paderborn. An administration and a workshop building as well as a company filling station and 41 parking spaces were built.
PROJECT DEVELOPMENT
CONSTRUCTION OF NEW HOTEL ABASTO
FELDMOCHING
Construction period | 01/2019 - 12/2020 |
Property surface area | 2,500 m² |
Rooms with prefabricated bathrooms | 120 |
Underground parking spaces | 29 |
HOTEL ABASTO
The 2,500 m² plot of land at Paul-Preuss-Strasse 2, near the underground and suburban railway, is home to a modern business hotel with 120 rooms, 29 underground parking spaces and a restaurant.
The hotel is a reinforced concrete, cross-wall structure with six floors and approximately 4,000 m² of above-ground floor space. It is heated using an extremely efficient ground water heat pump. Two lifts transport people from the basement up to the top floor.
The bathrooms are fully-equipped, prefabricated bathroom units that were integrated into the framework of the shell construction and placed in their final position. This resulted in far fewer vehicle journeys for the customary deliveries, compared to what is usually required for the individual trades.
Hotel Abasto was handed over to the tenants on 17 December 2020. We wish them every success.
STRUCTURAL ENGINEERING
NEW HEAD OFFICE FOR LIEBHERR
DETTINGEN
Construction period | 05/2020 - 09/2020 |
Reinforced steel | 600 to |
Ceiling formwork | 5,000 m² |
Volume of concrete | 7,600 m³ |
Wall formwork | 4,500 m² |
Number of solid, precast parts | 245 |
Order value | EUR 3,300,000 |
In Dettingen an der Iller, a three-storey building and a 2,430 m² production hall were built during a five-month construction period. The concrete precast parts required for the project were supplied by our subsidiary marbeton, while the entire external premises were completed by our civil engineering division. In order to complete the work within the short construction period, KUTTER’s structural and civil engineering team also worked on the construction site at weekends. At the end of September 2020, the construction work was completed at a cost of around EUR 3.3 million.
PROJECT DEVELOPMENT
CONSTRUCTION OF NEW HOTEL AMEDIA
DACHAU
Purchase of land | 2017 |
Planning permission | 11/2019 |
Start of construction | 02/2020 |
Total construction time | 02/2020 - 07/2021 |
Property surface area | 9,600 m² |
Size of building | 2,540 m² |
Soil replacement | 8,500 m² |
Quantity of steel | 216 to |
Volume of in-situ concrete | 3,650 m³ |
Number of solid precast parts | 411 |
Bathroom units | 205 |
All from a single source – from the shell construction to the ready-to-occupy building
Together with Amedia, KUTTER is currently developing a hotel with conferencing facilities covering 9,600 m² of floor space.
The construction period of 17 months is very short. In addition, we also had to overcome obstacles such as the time-consuming replacement of soil and the delayed delivery of 205 bathroom units and wet rooms from Italy as a result of the coronavirus crisis. Despite all this, thanks to the excellent collaboration and efforts of the individual civil engineering and structural engineering divisions at KUTTER, our subsidiary marbeton which supplied the precast concrete parts, general contractor Riebel and all other parties involved in the project, the agreed deadlines were met. On 31 July 2021, the hotel will be handed over to the tenant Amedia Group.
STRUCTURAL ENGINEERING
NEW DAIRY STALL
WIGGENSBACH
Construction period | 10/2019 - 01/2020 |
Length | 67 m |
Width | 30 m |
Space for | 80 dairy cows |
Order value | EUR 260,000 |
A new home for cows
A new cowshed with a floor space of around 2,000 m² for 80 dairy cows was built in Wiggensbach within three months.
Here TÜV certification qualifying the company as a specialized firm pursuant to the German Water Resources Act (WHG) was required for the construction project.
ARCHIVE – PROJECTS: MILLING
OBERAU TUNNEL
ESCHENLOHE,
GARMISCH PARTENKIRCHEN
Project | Oberau tunnel bypass |
Construction period | 2017-2019 |
LIGHT AT THE END OF THE TUNNEL
The overall process
Swiss company Marti AG was awarded the contract to build Oberau tunnel.
The tunnel is essentially constructed using underground excavation with blasting. Once the rough removal of the tunnel cross-section was complete, our specially adapted mining milling machines were deployed to profile the tunnel invert to the exact height level required.
Our machine operators were guided by defined survey points and transferred the data by means of a laser controller which engages directly with the machine controller.
The milled material is loaded directly onto the transport vehicle on site via the integrated loading conveyor. The steep belt conveyors are reinforced with solid steel inserts to prevent damage caused by sharp-edged stone.
Our machines and their performance capacity
The performance capacity of our machines is generally based on the type of stone. This project involved dolomite stone and limestone with associated single-axial compressive strength values.
A further indicator for performance capacity is the fissurisation of the material to be removed, which can be naturally inherent or due to damage caused by stone blasting.
The special task
Another key area of this project was the creation of utility trenches within the tunnel invert. To complete this special task, we used the W 2200 milling machine with lateral milling device, which we had modified in-house and has a milling width of around 65 cm. This way we were able to create trenches that were approximately 70 cm deep.
The benefit of this technique is the fact that the milling machine with an entire operational weight of more than 40 tonnes is positioned centrally above the milling drum.
Quality thanks to years of experience
We have many years of experience in both surface and profile milling and can produce cost-effective results through optimised applications, even in extreme conditions.
The tunnel builders in Central Europe are familiar with the opportunities presented by milling technology, and are already incorporating our technology in the planning and costing phases of their projects.