OVERVIEW OF OUR LATEST PROJECTS
Many customers from a broad range of sectors have already placed their trust in us and relied on KUTTER as their building contractor. We’ve summarised some of our projects for you here.
LATEST PROJECTS IN CIVIL ENGINEERING & ROAD CONSTRUCTION
CIVIL ENGINEERING & ROAD CONSTRUCTION
CULVERT STRUCTURE
REUTTI
Customer | State Building Authority Krumbach |
Construction period | 07/2022 - 10/2022 |
Dimensions | 4,50 x 2,25 m / 50 m |
Earthmoving | 7,500 m³ |
Streetmarking | 8,000 m |
Order value | EUR 1,816,276 |
Exciting project
Our road construction team worked at Reutti from July to October.
Construction was carried out on the culvert at the Landgraben. In addition, the road surface was renewed over a distance of 3.4 kilometers. Before the new culvert could be installed, the land ditch had to be relocated and the groundwater level lowered. This was followed by the relocation of the stream, the backfilling of the old culvert, the construction of the ceiling as well as protective barrier and marking work.
The road was closed during this time and traffic was diverted.
CIVIL ENGINEERING & ROAD CONSTRUCITON
DEVELOPMENT OF A NEW DEVELOPMENT
PENZING
Customer | WipflerPLAN and State Building Authority Weilheim |
Construction period | 11/2021 - 11/2022 |
Soil excavation | 11,000 m³ |
Sewer works | 450 m |
Drinking water pipes | 450 m |
Order value | EUR 2,409,033 |
New Connections
A new development area is currently being built between the western part of the Benediktbeurer Ring, Richthofenstrasse and Landsberger Strasse in the municipality of Penzing, and KUTTER was commissioned to develop it. The work included sewer, water pipe and road construction as well as light signal and noise protection work. In addition to the structural development of the construction area, the road construction work also included the redesign of the Landsberger Straße/Otto-Lilienthal-Straße intersection as well as asphalt pavement work in the roundabout and St 2054. We also built a 40-metre-long noise protection wall and took over the planting work. The construction work took place while traffic was moving, so that there were no restrictions for motorists.
CIVIL ENGINEERING & ROAD CONSTRUCTION
RAINWATER RETENTION BASIN
ENGETRIED
Customer | Kempten water authority |
Construction period | 09/2021 - 10/2023 |
Earthmoving | 200,000 m³ |
Limestone/cement binding | 7,000 to |
Sound insulation filling material | 120,000 m³ |
Drainage/discharge pipes DW | 120,000 m³ |
Order value | EUR 6,443,000 |
Heavy rainfall?
No problem!
On behalf of the Kempten water authority, we are building a rainwater retention basin in Engetried.
The KUTTER team began working on this construction site in September 2021 and it is scheduled for completion in October 2023. We are working at full speed, performing tasks such as moving approx. 200,000 m³ of earth. Drainage and discharge pipes are being laid with a total length of around 1,500 m and more than 7,000 tonnes of limestone/cement binder and approx. 120,000 m³ of sound insulation filling material will be used. The value of the entire construction project is around EUR 6.4 million.
Watch our new video for insights into the techniques and everyday work of our colleagues.
ASPHALT PAVING
NEW ROAD SURFACE
B472 IN INGENRIED
Customer | Weilheim building authority |
Construction period | 06/2022 - 07/2022 |
Total area | 65,000 m² |
Length of road markings | 26,000 m |
Order value | EUR 2,540,000 |
Built by Kutter!
On behalf of Weilheim building authority, the KUTTER team worked on the B472 in Ingenried.
Up to 30 tipper trailers and four-axle tippers were deployed as part of the road renovation project, to renovate 6.2 km of national road. It also involved replacing 250 m of drainage channels. Two large asphalt milling machines, one small asphalt milling machine and two large asphalt pavers with feeder were used.
ASPHALT PAVING FOR ROAD RENOVATION
A7 NEAR
BAD GRÖNENBACH
Customer | Autobahn GmbH, national motorway authority |
Construction period | 05/2022 - 07/2022 |
Renovation area | 60,000 m² |
Order value | EUR 2,310,000 |
Built by Kutter!
We captured a few images on the construction site on the A7 near Bad Grönenbach. The KUTTER civil engineering and road construction team worked on site from the start of May to the end of July, deploying two large milling machines, 30 semi-trailers and four asphalt pavers with feeder, to renovate the road surface on behalf of Autobahn GmbH, the national motorway authority.
CIVIL ENGINEERING & ROAD CONSTRUCTION
SPECIAL LOCAL BYPASS
FOR LENGENFELD
Customer | Municipality of Pürgen |
Construction period | 11/2021 - 11/2023 |
Earthmoving | 130,000 m³ |
Order value | EUR 7,646,600 |
CONSTRUCTION WORK WITH BAT PROTECTION
A special local bypass is being built on national road 2057 in Lengenfeld. The KUTTER team has been working on this special project since November 2021. The construction site has an ecological aspect, as bats fly around in this area. Therefore, a collision protection wall is being erected and two bridge structures have been built so that bats can fly underneath. Ensuring flood protection is another special aspect of this project.
LATEST PROJECTS: STRUCTURAL ENGINEERING
PROJECT DEVELOPMENT
THE GULDEIN
MUNICH
Construction period | 10/2020 - 12/2022 |
Land area | 1.182 m² |
Gross floor area | 1.800 m² |
Total living area | 1.434 m² |
Apartments | 21 |
Underground parking spaces | 17 |
of which multiple parkers | 8 |
Barrier-free, urban living
Executed by the KUTTER Munich branch, an urban residential building in the rear building style was created in the sought-after Munich Westend, which offers its residents barrier-free, ultra-modern apartments between 40 and 125 m2 of living space.
KUTTER has succeeded in creating a residential building that makes optimal use of the limited space available in a grown inner city district and combines comfort and energy efficiency with urban charm.
Architecturally, the building is designed in such a way that each apartment has an outdoor space in the form of a balcony or terrace. Away from the street there is also a garden area with a small playground, which gives the residents of the Guldein a private, green oasis. The residential units are supplemented by a cellar compartment, areas that can be used jointly, as well as a washing and drying room and bicycle rooms. A total of 17 underground parking spaces are also available.
To give you a little insight, click here for the online tour.
Strucutral Engineering
Loading and assembly hall
Hawangen
Construction period | 03/2022 - 12/2022 |
Customer | Hans Hundegger AG |
Order value | EUR 1,970,000 |
Earth and reinforced concrete work Industrial hall with office
In March, KUTTER started the contract for the building construction, civil engineering and road construction divisions with the preparatory earthwork for the new loading and assembly hall for Hundegger in Hawangen. The finished building was ready by June and could be handed over to the customer. By the end of the year, all necessary measures will also be completed in the outdoor area.
Thank you for the order and the trust you have placed in us!
Structural Engineering
Seniors residence
Kisslegg
Construction period | 08/2021 - 06/2022 |
Customer | Heim Infrastruktur |
Gross floor area | 5.500 m² |
Order value | EUR 2,613,600 |
Living well even in old age
From August 2021 to June 2022, KUTTER took over the shell construction of the senior citizens' residence in Kissleg.
33 one- to three-room apartments and 60 one-room apartments have been built on the 5,500 m² property. The facility should be ready for occupancy by June 2023.
KUTTER wishes continued good construction progress.

TURNKEY CONSTRUCTION
BUILDING OF A NEW MULTI-FAMILY DWELLING
LINDAU
Construction period | 01/2021 - 03/2022 |
Customer | GWG Lindauer Wohnungsgesellschaft mbH |
Gross floor area | 720 m² |
Order value | EUR 1,100,000 |
Six-family dwelling ready for occupancy
In the border town of Lindau, KUTTER handed over a ready-to-occupy, newly built six-family dwelling to the customer. The construction period was almost 14 months and work was completed according to plan.
TURNKEY CONSTRUCTION
SHOPPING CENTRE
BUXHEIM
Construction period, EDEKA | 04/2019 - 03/2020 |
Construction period, office and commercial building | 07/2020 - 03/2022 |
Customer | NVZ Buxheim GmbH & Co. KG |
Gross floor area: EDEKA | 4,284 m² |
Gross floor area: office and commercial building | 3,997 m² |
Order value | EUR 11,000,000 |
EDEKA, office and commercial building
A large construction project was successfully completed according to schedule in spring.
Buxheim now boasts a modern shopping centre, including an EDEKA supermarket with drinks store and bakery as well as an office and commercial building with underground car park. KUTTER completed the turnkey construction of both buildings.
STRUCTURAL ENGINEERING
DISTRICT HEATING PLANT
RAVENSBURG
Construction period | 03/2021 - 10/2021 |
Customer | District of Ravensburg |
Order value | EUR 526,500 |
Self-sufficiency for the school district
The aim of the new heating plant that was inaugurated in spring by Head of the District Authority, Harald Sievers, is for the area – which will also include a central, district council building and a newly built school – to become self-sufficient in terms of power by 2026.
KUTTER made a huge contribution towards the project with the construction of the heating plant and its eight-metre-high exposed concrete walls. We would like to thank the District of Ravensburg for awarding this contract to us.
LATEST PROJECTS: MILLING
NO MORE ROLLING AWAY
SHOPPING TROLLEY RETENTION SYSTEM
IN VILSHOFEN
Total length | approx. 900 m |
Width approx. | 5 cm |
The solution to a very common problem
Shopping trolleys rolling away in one supermarket car park in Vilshofen is a thing of the past. Using our special cutting machinery, we milled a profile into the asphalt in order to create a shopping trolley retention system measuring approximately 900 metres long. This was a really simple solution to a problem that we are all familiar with. The rear wheel of the shopping trolley fits neatly into the recess that is approximately 5 cm, holding the shopping trolley in place.
We mostly worked at night to prevent any disruption to ongoing operations.
DUST-FREE MILLING
HALL MILLING WORK
IN WEINSHEIM
Special solution for indoor milling
Dust-free and low-vibration milling indoors – we are the specialists. Our video shows exactly how we create cable ducting or profiles in a closed hall.
We filmed the work performed at our customer PRÜM-Türenwerk GmbH in Weinsheim. All the measures were discussed in advance with the customer and adapted precisely to their needs. This enabled us, for instance, to work in halls that still contained warehouse goods, as no dust emissions were created.
Milling work in building structures: fast, clean, precise and cost-effective with KUTTER.
MOBILE COLD MIXING PLANT
A MOBILE PLANT
IN SALZGITTER
Independent and versatile
A mobile plant that replaces lorry journeys between the mixing plant and remote construction sites: KUTTER’s mobile cold mixing plant. Thanks to the separate diesel motor, it can operate independently of the public power supply. The cold mix that is created is suitable for a wide range of different construction projects: motorways, high-quality bearing layers for road and path construction, reinforcement of car parks and parking areas. Watch the video to learn out the diverse applications.
MILLING RECYCLING
GROUND RENOVATION
IN THE BLACK FOREST
A uniform substrate
Uniform and sufficiently load-bearing substrates are the prerequisite for the permanent and damage-free foundation of structures. In the event that the in-situ ground does not have these properties, it can be prepared so that it can be built upon and bear loads, by incorporating limestone and/or cement.
KUTTER carries out a wide range of ground improvement and ground hardening activities, such as in the construction of roads, car parks, industrial premises, airports and rail tracks. We can perform diverse earthwork, such as the creation of dams, embankments or backfilling. The soil stabilisers are also ideal for creating seals in landfill construction.
Thanks to this fast and environmentally friendly procedure, there is no need for time-consuming and costly replacement of soil.
COLD RECYCLING
RENOVATION OF A COUNTRY ROAD IN RADEGAST
Ecological and economical
As many roads in Germany are severely damaged several layers deep, for some time now it has no longer been possible to just replace the surface over and over again. KUTTER are the specialists for the job: we repair the entire structure of the road and permanently increase its load-bearing capacity. KUTTER are pioneers of cold recycling, and we have devoted ourselves to this ecological and economical procedure. The technological leadership acquired in this complex area enables us to maintain the functional properties of roads in the long term.
We renovate traffic areas with as little logistical effort as possible. And we do this with asphalt recycling. Our video shows you exactly how it works and what machines are used.
Leipzig/Halle
Green light for the airport
in Leipzig/Halle
Construction period | 04/2021 - 05/2021 |
Material | 350,000 m² concrete/hydraulically bound mixture |
Renovation of the runway in Leipzig/Halle
The large project to renovate the northern runway at Leipzig airport started with the deployment of a special construction milling machine.
The work included building 9,375 metres of rain run-off channels, among other things. The ideal machine for this is the special construction milling machine from Kutter Leipzig with side-mounted milling drum. The milled material was extracted using suction excavators and disposed of professionally.
Over the next few days, another form of milling was used. This milling work was recently carried out in collaboration with Wirtgen and our workshop at the Leipzig branch.
In addition, ten W250 large milling machines were used to mill a total area of 307,000 m² of concrete and hydraulically bound mixture.
This equates to a total volume of 350,000 tonnes, or the equivalent of around 12,400 loaded semi-trailer tippers!
WHAT'S NEW?
KUTTER running team
half marathon
in Ottobeuren
Our KUTTER running team once again did a great job at the 2023 half marathon in Ottobeuren. The run took place in Ottobeuren for the eleventh time this year and is integrated for the first time as a kick-off event in the LEW running tour. A total of 300 runners started.
The popular sports event of the Bavarian-Swabian energy supplier LEW consists of a total of 8 races and will be continued in Illertissen on May 7th. As usual, the finale is the New Year's Eve run in Gersthofen on December 31st. Many thanks for the great organization and great atmosphere!
The result of our KUTTER runners is impressive. In the team ranking, our athletes took a great second place, for which we would like to congratulate them.
If our employees would like to join our running group in order to be physically active together, please feel free to contact Mr. Prigge. We welcome everyone who wants to take part. Beginners are also welcome!
Image source: Sport in Augsburg / Lechwerke (LEW)

KUTTER & RIEBEL
PART OF THE
BAM
Last Friday KUTTER & RIEBEL were part of the "BAM - Your fair for training and dual studies!" with over 80 exhibitors in the Mindelheim Forum.
The fair took place both virtually and one day on site. The lively exchange of information with all interested parties was a lot of fun for us and we look forward to seeing some of you again soon.
Are you currently still looking for an exciting apprenticeship or would you like to study dual studies? This is your chance!
You can find all open training positions and dual study places at https://www.kutter.de/en/projects and www.riebel-bau.de/karriere
Final sprint
End of construction rally
in Türkheim
Last Friday we were able to welcome classes 7a and 7bM from the Türkheim secondary school to the construction rally in our training workshop in Mindelheim for the last time.
This time, the students once again had the opportunity to try out our apprenticeships within the KUTTER Group at various stations and to put their manual skills to the test.
We are very pleased that some students have obviously shown an interest in an apprenticeship in construction and hope to see many of them again for an internship.
We will soon also be handing over the schoolyard benches that were made as part of the construction rally to the Mindelheim and Türkheim secondary schools.
Attention: you can always do an internship at KUTTER and RIEBEL without having been a participant in our construction rally. Just find out more at www.kutter.de/karriere or www.riebel-bau.de/karriere.
We look forward to hearing from you!