Built by
KUTTER!

OVERVIEW OF OUR LATEST PROJECTS

Many customers from a broad range of sectors have already placed their trust in us and relied on KUTTER as their building contractor. We’ve summarised some of our projects for you here.

CIVIL ENGINEERING & ROAD CONSTRUCTION STRUCTURAL ENGINEERING MILLING

LATEST PROJECTS IN CIVIL ENGINEERING & ROAD CONSTRUCTION

CIVIL ENGINEERING & ROAD CONSTRUCTION

CULVERT STRUCTURE
REUTTI

CustomerState Building Authority Krumbach
Construction period07/2022 - 10/2022
Dimensions4,50 x 2,25 m / 50 m
Earthmoving7,500 m³
Streetmarking8,000 m
Order valueEUR 1,816,276

Exciting project

Our road construction team worked at Reutti from July to October.
Construction was carried out on the culvert at the Landgraben. In addition, the road surface was renewed over a distance of 3.4 kilometers. Before the new culvert could be installed, the land ditch had to be relocated and the groundwater level lowered. This was followed by the relocation of the stream, the backfilling of the old culvert, the construction of the ceiling as well as protective barrier and marking work.

The road was closed during this time and traffic was diverted.

CIVIL ENGINEERING & ROAD CONSTRUCITON

DEVELOPMENT OF A NEW DEVELOPMENT
PENZING

CustomerWipflerPLAN and State Building Authority Weilheim
Construction period11/2021 - 11/2022
Soil excavation11,000 m³
Sewer works450 m
Drinking water pipes450 m
Order valueEUR 2,409,033

New Connections

A new development area is currently being built between the western part of the Benediktbeurer Ring, Richthofenstrasse and Landsberger Strasse in the municipality of Penzing, and KUTTER was commissioned to develop it. The work included sewer, water pipe and road construction as well as light signal and noise protection work. In addition to the structural development of the construction area, the road construction work also included the redesign of the Landsberger Straße/Otto-Lilienthal-Straße intersection as well as asphalt pavement work in the roundabout and St 2054. We also built a 40-metre-long noise protection wall and took over the planting work. The construction work took place while traffic was moving, so that there were no restrictions for motorists.
 

CIVIL ENGINEERING & ROAD CONSTRUCTION

RAINWATER RETENTION BASIN
ENGETRIED

CustomerKempten water authority
Construction period09/2021 - 10/2023
Earthmoving200,000 m³
Limestone/cement binding7,000 to
Sound insulation filling material120,000 m³
Drainage/discharge pipes DW120,000 m³
Order valueEUR 6,443,000

Heavy rainfall?
No problem!

On behalf of the Kempten water authority, we are building a rainwater retention basin in Engetried.

The KUTTER team began working on this construction site in September 2021 and it is scheduled for completion in October 2023. We are working at full speed, performing tasks such as moving approx. 200,000 m³ of earth. Drainage and discharge pipes are being laid with a total length of around 1,500 m and more than 7,000 tonnes of limestone/cement binder and approx. 120,000 m³ of sound insulation filling material will be used. The value of the entire construction project is around EUR 6.4 million.

Watch our new video for insights into the techniques and everyday work of our colleagues.


ASPHALT PAVING

NEW ROAD SURFACE
B472 IN INGENRIED

CustomerWeilheim building authority
Construction period06/2022 - 07/2022
Total area65,000 m²
Length of road markings26,000 m
Order valueEUR 2,540,000

Built by Kutter!

On behalf of Weilheim building authority, the KUTTER team worked on the B472 in Ingenried.

Up to 30 tipper trailers and four-axle tippers were deployed as part of the road renovation project, to renovate 6.2 km of national road. It also involved replacing 250 m of drainage channels. Two large asphalt milling machines, one small asphalt milling machine and two large asphalt pavers with feeder were used.

ASPHALT PAVING FOR ROAD RENOVATION

A7 NEAR
BAD GRÖNENBACH

CustomerAutobahn GmbH, national motorway authority
Construction period05/2022 - 07/2022
Renovation area60,000 m²
Order valueEUR 2,310,000

Built by Kutter!

We captured a few images on the construction site on the A7 near Bad Grönenbach. The KUTTER civil engineering and road construction team worked on site from the start of May to the end of July, deploying two large milling machines, 30 semi-trailers and four asphalt pavers with feeder, to renovate the road surface on behalf of Autobahn GmbH, the national motorway authority.

CIVIL ENGINEERING & ROAD CONSTRUCTION

SPECIAL LOCAL BYPASS
FOR LENGENFELD

CustomerMunicipality of Pürgen
Construction period11/2021 - 11/2023
Earthmoving130,000 m³
Order valueEUR 7,646,600

CONSTRUCTION WORK WITH BAT PROTECTION

A special local bypass is being built on national road 2057 in Lengenfeld. The KUTTER team has been working on this special project since November 2021. The construction site has an ecological aspect, as bats fly around in this area. Therefore, a collision protection wall is being erected and two bridge structures have been built so that bats can fly underneath. Ensuring flood protection is another special aspect of this project.


MORE REFERENCES >

CIVIL ENGINEERING & ROAD CONSTRUCTION

GARMISCH-PARTENKIRCHEN
THROUGH-ROAD

CustomerGarmisch-Partenkirchen municipal utility company
Construction period03/2021 - 11/2021
Order valueEUR 2,087,000

Special feature

- HPP piping DN315: 300 m 

- Reinforced concrete piping DN700: 100 m

- Reinforced concrete piping DN800: 100 m

- Reinforced concrete piping DN1000: 85 m

- GFRP piping DN1000: 35 m

- GFRP piping DN1100: 280 m 

Storage structure:

- GFRP piping DN2000: 27 m

- Throttle surge chamber DN3000

- Drainage well DN3000 

- Amiblu: https://www.amiblu.com/de/videos/

(The sand trap has not yet been installed in the piping)

The project is set to be completed in record time. The agreed, planned construction period was from March to November. However, it is likely that our KUTTER team will be able to complete the work ahead of schedule in September.

ASPHALT PAVING

ROAD RENOVATION OF A96
INLINE PAVE METHOD

Milling work43,000 m²
Asphalt binder, two layers (InLine Pave method)35,600 m² of AC 16BS-NV and AC 16 BS-SG
Asphalt binder, one layer7,400 m² of AC 16 BS-SG
Asphalt top layer43,000 m² of DSH-V 05
Replacement of road gullies42 units
Replacement of road shoulder6,400 m
Order valueEUR 1,650,000

Perfectly orchestrated night work on the A96

One of the first asphalt paving contracts of 2020 began in April on the A96 near Etterschlag. We carried out the road renovation work on both sides of the road during flowing traffic, by applying the InLine Pave method. Only a couple of leading construction companies in Germany offer this extremely innovative method, which is especially suitable for “hot on hot” installations. At KUTTER, this cost-effective method forms part of our core service offering. Watch our new video for insights into the techniques and everyday work of our colleagues.

CIVIL ENGINEERING & ROAD CONSTRUCTION

AUGSBURGER STRASSE
MEMMINGERBERG

CustomerMunicipality of Memmingerberg
Local construction management + PlanningKlinger engineering firm
Construction period04/2018 – 12/2019
Length of constructionapprox. 1,100 m long / 11 m wide
Total value of construction projectEUR 4,400,000

The construction project

A few hundred metres from our head office at Augsburger Strasse 55 in Memmingen, we completed a large-scale civil engineering and road construction project for the municipality of Memmingerberg.

It involved moving a total of 11,600 m³ of soil as well as installing 81 road drainage inlets and 65 prefabricated shafts. Our colleagues also processed 12,950 m³ of material excavated from utility trenches, laid 3,350 sewer pipes and installed a mains water pipe for the municipality measuring 1,130 m long.

The edging was covered with 5,300 m³ of antifreeze gravel on top of which kerbstones and large granite paving were laid over a total length of 6,900 m.

The asphalt paving team then installed 14,000 m² of bearing, binding and top layers.

Throughout the entire project, the total cost for disposing of the excavated material was EUR 790,000. KUTTER was able to complete the project on schedule and in time for winter.


CIVIL ENGINEERING & ROAD CONSTRUCTION

RENOVATION OF THE
A96

Total length2 x 5,900 m
Width11.5 m
Junctions3
Construction period03/2019 – 12/2019
CustomerBavaria motorway authority
Total value of construction projectapprox. EUR 10,500,000
JunctionsDual carriageways, with three junctions on each side
Material excavated from utility trenches9,500 m³
Prefabricated shafts150 units
Seepage pipes5,100 m
Sewer pipes5,100 m
Milled asphalt layers64,000 tonnes
Milled hydraulically bound bearing layer with tachymeter140,000 m²
Asphalt layers composed of bearing, binding and top layersapprox. 77,000 tonnes
Creation of road shoulder21,000 m

Collaboration with the world’s largest road paver Vögele

From March to December 2019, KUTTER was commissioned by the Kempten agency of the Bavaria motorway authority to renovate the A96 over a total length of 2x 5,900 m and a width of 11.5 m.

The construction site included three junctions. Collaboration from the start: with the world’s largest road paver Vögele.

We would like to thank Vögele for providing us with the impressive video featuring the road renovation project.

CIVIL ENGINEERING & ROAD CONSTRUCTION

REDESIGN OF
KEMPTEN TOWN PARK

Construction period10/2108 - 12/2019
Order valueEUR 4,700,000
Ductwork for cables2,500 m
Laid cabling3,200 m
Earthworks3,000 m³
Installation of gravel & paving1,800 m³
Large granite paving3,400 m²
Edging of meadow area500 m

Built by Kutter!

The town park in Kempten was redesigned in October 2018. KUTTER was involved as the lead construction company. 2,500 m of ductwork for cables were laid with a total of 3,200 m of cabling.

The park has a new paved surface covering a total area of 6,400 m² and consisting of large granite paving from four different quarries. A border of approx. 500 m in length was also created around the meadow area.

 

In addition, the design of the central bus stops was optimised and permanent installations were also created for the Allgäu Festival Week. Particular highlights also include the fountains with lighting effect and underground water supply shaft.

Our teams made sure the trees were fully protected of course during all the construction work.

We are delighted that the town of Kempten has documented the construction work and made the material available to us.

CIVIL ENGINEERING & ROAD CONSTRUCTION

ALLGÄU AIRPORT
MEMMINGEN

Construction period03/2019 until end 10/2019
WorkLaying of a ductwork system, widening of the runway
Order valueEUR 14,000,000
Total value of construction projectEUR 22,000,000
Other detailsEU tender

TIME FOR THE NIGHT SHIFT

KUTTER beats off EU-wide competition

From a military airport to one of the most important backbones of the Free State of Bavaria: Allgäu Airport in Memmingen has been an important hub for some time now. It offers flights to Egypt, Corsica, Italy, Morocco, Spain, Portugal, Great Britain and many more destinations. With a new record flight plan of over 50 destinations, it is attracting increasing numbers of holidaymakers and business travellers. In order to be able to offer additional, varied destinations to its many air passengers in future, the airport is now being expanded – not least so it can continue to fulfil the increasingly strict international security guidelines.

After a ten-month marathon of negotiations, this challenging and exciting project was awarded to KUTTER. The costing work alone for this EU-wide tender took almost two months. This was followed by a lengthy planning process with regard to employee self-monitoring as well as a time-consuming approval process for each individual worker and each individual machine – after all, the project was for an airport, classed therefore as a high-security zone. Ultimately, KUTTER was able to complete the tender stage to the utmost satisfaction of the customer and emerged successful in face of the competitors from across the EU. Last November, the groundbreaking ceremony for the renovation project took place in the presence of Bavarian Minister President Markus Söder.

The excavators roll onto site at 9.30pm

 

Since March 2019, it’s been a daily occurrence for the KUTTER team: “Time for the night shift!”. As soon as the last flights have left the runway, the large construction machines start moving. First of all, cable trenches for a ductwork system were dug out along the entire runway, in which the electrics for the runway lighting will be installed at a later point. The biggest challenge: By 6am precisely when the first planes start moving, all the machinery must be returned the garage, and all the holes and trenches must be filled in until the four KUTTER crews get back to work again in the evening at 9.30pm.

Complete closure of the airport in autumn

Things will get really exciting in early autumn, when the airport will be completely closed to air traffic for the last two weeks of September. This is when the work will ramp up and be performed day and night in shifts to extend the width of the runway from 30 to 45 metres across its entire length. It will be a race against time as no delays can be afforded, considering the fact that the largest airline Ryanair will suspend all air traffic during this period.

Financed by the free state

The mammoth project is being partially financed by the Free State of Bavaria as well as the airport’s shareholders. The order value of the civil engineering work performed by KUTTER alone equates to EUR 15 million. To get an overview of the large construction project, Bavarian State Minister for Construction and Transport, Dr Hans Reichert, recently visited the site. Together with the airport’s CEO, Ralf Schmid, and Member of Bavarian State Parliament, Klaus Holetschek, KUTTER CEO, Peter Groll, and Head of Division, Andreas Binder visited the site with the politician, explaining the individual work steps and highlighting the particular challenges for both the workers and the machinery.

KUTTER in the media

Naturally, the project is being covered by the media. The press reports regularly on the progress, as do TV channels such as Allgäu-TV, which is often on site and broadcasts impressive footage of what is currently happening on the construction site.

The renovation works are scheduled to be completed in 2020. Besides expanding the runway and replacing the instrument landing system, the luggage halls are also being extended, the apron areas are being widened and a rainwater retention basin is being built.

KUTTER is proud to play a leading role in shaping such an important, regional project and wishes all of the employees involved every success!


LESS REFERENCES >

LATEST PROJECTS: STRUCTURAL ENGINEERING

Structural Engineering

New company building
in Memmingen

Construction period11/2022-04/2023
ClientMössmer Kissner GbR
Order valueEUR 2,050,000

Started in the fall...
... ready to move in in August

In November last year, the go-ahead was given for the company building of Mössmer Kissner GbR. The building construction work was completed as planned in April, now it's the KUTTER civil engineering team's turn to take care of the outdoor facilities. The company building is to be occupied in August.

The company premises include a two-storey main building, which houses a workshop, showrooms and offices on a floor area of ​​approx. 1,850 m2, as well as two outbuildings with a washing facility and a cold storage/tire warehouse.

We are pleased to have completed the project in the usual professional manner despite the sporty construction time and are now handing it over to our colleagues from civil engineering.

Turnkey construction

Three apartment buildings
in Diessen a. Ammersee

Construction period02/2022 - 12/2023
CustomerJosef Happach
Land area2,548 m²
Living area1,521 m²
Order valueEUR 6,100,000

Housing for 18 families

In beautiful Dießen am Ammersee, three six-family houses with underground parking, open parking spaces and sheds are being built in a construction period of almost two years under the turnkey construction department. The work is progressing well, so that we can successfully complete the project at the end of the year.

We thank you for the order and wish our colleagues on the construction site continued success.

Turnkey construction

General renovation of
residential buildings in Lindau

Construction period04/2020 - 12/2022
CustomerGWG Lindauer Wohnungsgesellschaft mbH
Living area1,529 m²
Order valueEUR 4,400,000

Feel-good living
in the former brewery

Until the end of last year, KUTTER was entrusted with the turnkey general renovation of the former Lindauer brewery. 19 modern residential units were created here, which have retained the historical charm of the building despite the cutting-edge architecture.

Thank you for the order and the trust you have placed in us.


STRUCUTRAL ENGINEERING

REDEVELOPMENT OF THE MONASTERY ECONOMY
OTTOBEUREN

Construction period01/2022 - 03/2023
CustomerBenedictine Abbey Ottobeuren
Rebar104 to
Reinforced concrete ceilings1.239 m²
Wood-concrete composite ceilings875 m²
Concrete1.420 m³
Masonry surfaces927 m²
Order valueEUR 1,300,00.00

From monastic economy
becomes residential complex

For a little over a year, one of our building construction teams was involved in the renovation of the former monastery economy in Ottobeuren, which will comprise 24 residential units with underground parking and outbuildings after completion.

KUTTER took care of the shell construction and wishes good luck for the further construction project.

PROJECT DEVELOPMENT

THE GULDEIN
MUNICH

Construction period10/2020 - 12/2022
Land area1.182 m²
Gross floor area1.800 m²
Total living area1.434 m²
Apartments21
Underground parking spaces17
of which multiple parkers8

Barrier-free, urban living

Executed by the KUTTER Munich branch, an urban residential building in the rear building style was created in the sought-after Munich Westend, which offers its residents barrier-free, ultra-modern apartments between 40 and 125 m2 of living space.

KUTTER has succeeded in creating a residential building that makes optimal use of the limited space available in a grown inner city district and combines comfort and energy efficiency with urban charm.

Architecturally, the building is designed in such a way that each apartment has an outdoor space in the form of a balcony or terrace. Away from the street there is also a garden area with a small playground, which gives the residents of the Guldein a private, green oasis. The residential units are supplemented by a cellar compartment, areas that can be used jointly, as well as a washing and drying room and bicycle rooms. A total of 17 underground parking spaces are also available.

To give you a little insight, click here for the online tour.

Strucutral Engineering

Loading and assembly hall
Hawangen

Construction period03/2022 - 12/2022
CustomerHans Hundegger AG
Order valueEUR 1,970,000

Earth and reinforced concrete work Industrial hall with office

In March, KUTTER started the contract for the building construction, civil engineering and road construction divisions with the preparatory earthwork for the new loading and assembly hall for Hundegger in Hawangen. The finished building was ready by June and could be handed over to the customer. By the end of the year, all necessary measures will also be completed in the outdoor area.

Thank you for the order and the trust you have placed in us!


MORE REFERENCES>

Structural Engineering

Seniors residence
Kisslegg

Construction period08/2021 - 06/2022
CustomerHeim Infrastruktur
Gross floor area5.500 m²
Order valueEUR 2,613,600

Living well even in old age

From August 2021 to June 2022, KUTTER took over the shell construction of the senior citizens' residence in Kissleg.

33 one- to three-room apartments and 60 one-room apartments have been built on the 5,500 m² property. The facility should be ready for occupancy by June 2023.

KUTTER wishes continued good construction progress.

TURNKEY CONSTRUCTION

BUILDING OF A NEW MULTI-FAMILY DWELLING
LINDAU

Construction period01/2021 - 03/2022
CustomerGWG Lindauer Wohnungsgesellschaft mbH
Gross floor area720 m²
Order valueEUR 1,100,000

Six-family dwelling ready for occupancy

In the border town of Lindau, KUTTER handed over a ready-to-occupy, newly built six-family dwelling to the customer. The construction period was almost 14 months and work was completed according to plan.

TURNKEY CONSTRUCTION

SHOPPING CENTRE
BUXHEIM

Construction period, EDEKA04/2019 - 03/2020
Construction period, office and commercial building07/2020 - 03/2022
CustomerNVZ Buxheim GmbH & Co. KG
Gross floor area: EDEKA4,284 m²
Gross floor area: office and commercial building3,997 m²
Order valueEUR 11,000,000

EDEKA, office and commercial building

A large construction project was successfully completed according to schedule in spring.

Buxheim now boasts a modern shopping centre, including an EDEKA supermarket with drinks store and bakery as well as an office and commercial building with underground car park. KUTTER completed the turnkey construction of both buildings.


STRUCTURAL ENGINEERING

DISTRICT HEATING PLANT
RAVENSBURG

Construction period03/2021 - 10/2021
CustomerDistrict of Ravensburg
Order valueEUR 526,500

Self-sufficiency for the school district

The aim of the new heating plant that was inaugurated in spring by Head of the District Authority, Harald Sievers, is for the area – which will also include a central, district council building and a newly built school – to become self-sufficient in terms of power by 2026.

KUTTER made a huge contribution towards the project with the construction of the heating plant and its eight-metre-high exposed concrete walls. We would like to thank the District of Ravensburg for awarding this contract to us.

PROJECT DEVELOPMENT

KÖNIGSGRABEN
MEMMINGEN

Construction period02/2020 - 11/2021
Property surface area3,100 m²
Gross floor area3,248 m²
Total living space2,822 m²
Multi-family dwellings3
Apartments28
Underground parking spaces28

Modern and close to the centre

Just a few steps from Memmingen’s old town, KUTTER created a modern residential area as part of a construction project lasting almost two years.

A total of three buildings 28 flats have been created, and each residential unit also has a underground parking space.

High-quality materials, modern floor plans and the latest technical equipment turned the project into a real residential experience.

All the units have already been sold and are currently occupied.

Special feature: the fully automatic parking system

Watch the Video here!

STRUCTURAL ENGINEERING

JOHANNITER DAY NURSERY
MEMMINGEN

Construction period04/2021 - 03/2022
CustomerJohanniter Unfall Hilfe e.V.
Property surface area4,600 m²
Order valueEUR 686,755

A new day nursery building belonging to Johanniter Unfall Hilfe e.V. is being built on Lisztstrasse in Memmingen

A total of 582 m² distributed across two floors will offer space for 100 children in the future. On both floors, two group rooms each are currently being built, with adjoining rooms and sanitary facilities. On the L-shaped ground floor, there is also a multi-purpose room, staff rooms and a kitchen area. On the eastern single-storey part of the building, a partly paved roof terrace is being built that will be connected to the external premises via a staircase and a slide.

KUTTER will complete the construction work according to schedule in March.


LESS REFERENCES >

LATEST PROJECTS: MILLING

NO MORE ROLLING AWAY

SHOPPING TROLLEY RETENTION SYSTEM
IN VILSHOFEN

Total lengthapprox. 900 m
Width approx.5 cm

The solution to a very common problem

Shopping trolleys rolling away in one supermarket car park in Vilshofen is a thing of the past. Using our special cutting machinery, we milled a profile into the asphalt in order to create a shopping trolley retention system measuring approximately 900 metres long. This was a really simple solution to a problem that we are all familiar with. The rear wheel of the shopping trolley fits neatly into the recess that is approximately 5 cm, holding the shopping trolley in place. 

We mostly worked at night to prevent any disruption to ongoing operations.

DUST-FREE MILLING

HALL MILLING WORK
IN WEINSHEIM

Special solution for indoor milling

Dust-free and low-vibration milling indoors – we are the specialists. Our video shows exactly how we create cable ducting or profiles in a closed hall.

We filmed the work performed at our customer PRÜM-Türenwerk GmbH in Weinsheim. All the measures were discussed in advance with the customer and adapted precisely to their needs. This enabled us, for instance, to work in halls that still contained warehouse goods, as no dust emissions were created.

Milling work in building structures: fast, clean, precise and cost-effective with KUTTER.

MOBILE COLD MIXING PLANT

A MOBILE PLANT
IN SALZGITTER

Independent and versatile

A mobile plant that replaces lorry journeys between the mixing plant and remote construction sites: KUTTER’s mobile cold mixing plant. Thanks to the separate diesel motor, it can operate independently of the public power supply. The cold mix that is created is suitable for a wide range of different construction projects: motorways, high-quality bearing layers for road and path construction, reinforcement of car parks and parking areas. Watch the video to learn out the diverse applications.


MILLING RECYCLING

GROUND RENOVATION
IN THE BLACK FOREST

A uniform substrate

Uniform and sufficiently load-bearing substrates are the prerequisite for the permanent and damage-free foundation of structures. In the event that the in-situ ground does not have these properties, it can be prepared so that it can be built upon and bear loads, by incorporating limestone and/or cement.

KUTTER carries out a wide range of ground improvement and ground hardening activities, such as in the construction of roads, car parks, industrial premises, airports and rail tracks. We can perform diverse earthwork, such as the creation of dams, embankments or backfilling. The soil stabilisers are also ideal for creating seals in landfill construction.

Thanks to this fast and environmentally friendly procedure, there is no need for time-consuming and costly replacement of soil.

COLD RECYCLING

RENOVATION OF A COUNTRY ROAD IN RADEGAST

Ecological and economical

As many roads in Germany are severely damaged several layers deep, for some time now it has no longer been possible to just replace the surface over and over again. KUTTER are the specialists for the job: we repair the entire structure of the road and permanently increase its load-bearing capacity. KUTTER are pioneers of cold recycling, and we have devoted ourselves to this ecological and economical procedure. The technological leadership acquired in this complex area enables us to maintain the functional properties of roads in the long term.

We renovate traffic areas with as little logistical effort as possible. And we do this with asphalt recycling. Our video shows you exactly how it works and what machines are used.

Leipzig/Halle

Green light for the airport
in Leipzig/Halle

Construction period04/2021 - 05/2021
Material350,000 m² concrete/hydraulically bound mixture

Renovation of the runway in Leipzig/Halle

The large project to renovate the northern runway at Leipzig airport started with the deployment of a special construction milling machine.

The work included building 9,375 metres of rain run-off channels, among other things. The ideal machine for this is the special construction milling machine from Kutter Leipzig with side-mounted milling drum. The milled material was extracted using suction excavators and disposed of professionally.

Over the next few days, another form of milling was used. This milling work was recently carried out in collaboration with Wirtgen and our workshop at the Leipzig branch.

In addition, ten W250 large milling machines were used to mill a total area of 307,000 m² of concrete and hydraulically bound mixture.

This equates to a total volume of 350,000 tonnes, or the equivalent of around 12,400 loaded semi-trailer tippers!


MORE REFERENCES >

LUDWIGSHAFEN

Bridge demolition on the B37
in Ludwigshafen

Construction period05/2020 - 07/2020
Total surface area10,000 m²
Milling machine usedradio-controlled W 50 milling machine

The overall process

After noticing the damage on the bridge, the City of Ludwigshafen closed the bridge and surrounding area to all forms of traffic. 

As this is a traffic intersection, it caused major disruption for the entire population. 

In order to remove the partly contaminated coating without having to dispose of the entire demolition material, a radio-controlled milling machine with a maximum weight of ten tonnes needed to be used. 

Up until this point, our company did not have a radio-controlled milling machine, therefore within a very short time, the milling specialists at KUTTER developed a W 50 milling machine offering all the required functions, which were converted to radio control. 

Special feature: The machine operator remained on a part of the bridge that was not being worked upon and was held secure by a safety harness on a truck-mounted crane, from where they could operate the machine via remote radio controls. 

The material was placed down on the bridge deck and picked up separately during the demolition work.

ADELSDORF

CONSTRUCTION OF A NEW BYPASS
IN ADELSDORF

Project Adelsdorf bypass

KUTTER is working on the construction of a new bypass in Adelsdorf. During the initial phase, 3,500 cubic metres of limestone were removed using heavy equipment (see images).

The asphalt junction at the existing traffic lane is currently being milled. Over the coming weeks, a further 1,100 cubic metres of rock will be milled for the second section of the bypass.

KARL-MARX-ALLEE

MILLING SPECIALISTS
IN BERLIN MITTE

Construction period11/2019 - 11/2019
Total area10,000 m²
Milled area7,500 m²
Milled depth0-12 cm
Materialconcrete without reinforcement
ControllerTrimble tachymeter controller
Milling machine usedWirtgen W 100 CFi

MILLIMETRE PRECISION WORK IN BERLIN MITTE

In November 2019, the milling specialists at KUTTER GmbH & Co. KG milled the challenging profile of a drainage channel into a concrete surface.

A 3D system was used for the levelling work. Special feature: The project was for the Senate Administration for the Environment, Urban Mobility, and Climate Action on Karl-Marx-Allee in the heart of Berlin, under which runs an underground train line. For this reason, it was not possible to use large milling machines. Instead, KUTTER performed the 3D milling using a compact device with 1 m milling width, and developed an innovative solution that can safely discharge rainwater.

Work to redesign Karl-Marx-Allee, an avenue in the heart of Berlin measuring up to 72.5 m wide in parts, has been ongoing in several stages since the summer of 2018. In future, there will be less room for cars. Instead there will be wider cycle paths as well as attractive walking paths and open spaces. After removing the bituminous road surfaces, the drainage points and the pavement were replaced.

Drainage channel in the concrete surface

The next step – to create a profile in the concrete surface beneath the asphalt – was challenging from a construction point of view. The profile of a drainage channel was required in order to later ensure the drainage of rainwater along a length of approx. 800 m and a width of 5.75 m. The plans stipulated that the slope had to vary between 2.5% and 3% at distances of 3-5 m. On the remaining 9.25 m width of the road, the profile needed to have a cross slope of 2.5% from the centre to the edge of the road. Based on this geometry, this resulted in a milled depth that constantly varied between 0 and 12 cm. But what’s more, the Berlin underground railway runs beneath parts of Karl-Marx-Allee. Therefore, due to load restrictions, large milling machines could not be used on around 75% of the construction area.

3D milling with a compact machine

In light of this task, the team of milling specialists at KUTTER developed a concept together with the main contractor Matthäi GmbH & Co. KG for the precise profiling of concrete. The machine of choice was a compact milling machine with a 1 m milling width, equipped with a 3D levelling system. This is rather unusual as normally only large machines with a milling width of at least 2 m are used for 3D milling.

Tried and tested for many years

“For almost a decade, we’ve been successfully creating new profiles by means of 3D levelling and have tried out different systems. The variants

incorporating a Totalstation have proven to be the best for a wide range of tasks. Therefore, we were certain this method would be successful for the project in Berlin Mitte,” explains Roland Schmid, Head of Milling at KUTTER in Memmingen. This meant that the milling specialists were able to confidently deliver the required precision of ± 5 mm in accordance with additional technical terms of contract, and create the best conditions for laying the asphalt top structure.


OBERAU TUNNEL

ESCHENLOHE,
GARMISCH PARTENKIRCHEN

ProjectOberau tunnel bypass
Construction period2017-2019

LIGHT AT THE END OF THE TUNNEL

The overall process

Swiss company Marti AG was awarded the contract to build Oberau tunnel.

The tunnel is essentially constructed using underground excavation with blasting. Once the rough removal of the tunnel cross-section was complete, our specially adapted mining milling machines were deployed to profile the tunnel invert to the exact height level required.

Our machine operators were guided by defined survey points and transferred the data by means of a laser controller which engages directly with the machine controller.

The milled material is loaded directly onto the transport vehicle on site via the integrated loading conveyor. The steep belt conveyors are reinforced with solid steel inserts to prevent damage caused by sharp-edged stone.

Our machines and their performance capacity

The performance capacity of our machines is generally based on the type of stone. This project involved dolomite stone and limestone with associated single-axial compressive strength values.

A further indicator for performance capacity is the fissurisation of the material to be removed, which can be naturally inherent or due to damage caused by stone blasting.

The special task

Another key area of this project was the creation of utility trenches within the tunnel invert. To complete this special task, we used the W 2200 milling machine with lateral milling device, which we had modified in-house and has a milling width of around 65 cm. This way we were able to create trenches that were approximately 70 cm deep.

The benefit of this technique is the fact that the milling machine with an entire operational weight of more than 40 tonnes is positioned centrally above the milling drum.

Quality thanks to years of experience

We have many years of experience in both surface and profile milling and can produce cost-effective results through optimised applications, even in extreme conditions.

The tunnel builders in Central Europe are familiar with the opportunities presented by milling technology, and are already incorporating our technology in the planning and costing phases of their projects.

 

 

LESS REFERENCES >

ARCHIVE >
LATEST NEWS

WHAT'S NEW?

School festival

We were
part

Two weeks ago we were guests at the school festival of the Lindenschule Memmingen. As part of the programme, the students and their parents had the opportunity to take part in various tasks and stations. Various companies were also represented and the students were able to demonstrate their manual dexterity.

It was a successful school festival and if we have aroused your interest in the construction industry, then we are happy to welcome you, during an internship for example.

Are you currently still looking for an exciting apprenticeship from September 2023? This is your chance - become part of KUTTER!

You can find all open training positions at https://www.kutter.de/en/karriere

Company contact fair

KUTTER on the Pyramid
in Augsburg

We were very pleased about the numerous visits to our booth at the Pyramid careers fair in Augsburg.

The trade fair visitors were not only able to find out about the best way to start a career, but also about student assignments as interns or working students and the different possibilities for the bachelor thesis.

We had many great conversations and are also pleased that you are visiting our careers section here on the website. There you will find all further information on the subject of studies and careers at KUTTER.

GROUNDBREAKING

NEW CONSTRUCTION OF A
PENNY MARKET IN OFFENSTETTEN

On May 10, 2023, KUTTER invited to the groundbreaking ceremony for the long-awaited Penny market in the Offenstetten district of Abensberg. For the citizens of Offenstetten, a long-standing wish has come true with the construction of their own supermarket. The project is now possible not least because with KUTTER not only a construction company has been found, but also an investor for the building, because KUTTER will rent the building and the area to Penny Markt GmbH in the future.

Construction work began in October 2022 with the creation of the left-turn lane into the future supermarket site, with opening scheduled for early 2024. A Penny supermarket will be built with around 1000 m2 of retail space and 75 planned parking spaces. Environmental considerations were also taken into account, for example a green roof is planned. Heat pumps and recovery from commercial refrigeration are to provide the energy supply. A PV system is also planned for the roof. The location at the entrance to the town is also ideal, where there is already a restaurant, a bakery and a gas station with a car dealership. "People who shop locally avoid unnecessary traffic," Managing Director Ulrich Dick put it in a nutshell. In his greeting, he also emphasized the good cooperation with the Abensberg city administration, that the project could be advanced very quickly.

In the picture: from left: City Councilor Fritz Zeilbeck, First Mayor Uwe Brandl, City Councilor and Advisor for Integration and Asylum, Magdalena Groll-Zieglmeier, City Councilor and Environmental Advisor Richard Zieglmeier, Third Mayor, City Councilor and Integration Advisor Marion Huber-Schallner, Second Mayor Bernhard Resch, Project developer Sabine Klemm from the construction company KUTTER, city councilor and economics officer Uli Glamsch, city councilor Harald Hillebrand, Armin Fäßlin, head of turnkey construction at KUTTER, Penny expansion manager Michael Jasch and Ulrich Dick, KUTTER managing director. Photos: Ingo Knott

MORE NEWS >

VHK Career forum

KUTTER meets students
at munich university

Yesterday we were at the Munich University of Applied Sciences at the career fair VHK Career Forum BAU!

More than 300 students from the construction industry from various universities from all over Bavaria and Baden-Württemberg were on site and were able to find out about the best way to start a career. Demand was also high on the subject of student assignments as interns or working students and the various options for the bachelor’s thesis.

We had many great conversations and are happy about the lively interest in KUTTER.

KUTTER Instructor Day

Coaching for trainers
in the conference hotel

In March, the trainers of all training professions from KUTTER go to a trainers' day in the conference hotel.

The priority was the exchange of experiences and the promotion of independent professional action in order to make our trainees fit for everyday working life.

The coaching focused on what it takes to successfully design the training for our trainees and what communication channels are needed.

The participants obviously had fun and we are sure that the common sense of togetherness was strengthened.

KUTTER

DELIVERY OF
SCHOOLYARD BENCHES

A few weeks ago we were able to welcome classes 7a and 7bM from the Türkheim middle school to our training workshop in Mindelheim for the construction rally.

The students had the opportunity to get to know the activities of our apprenticeships within the KUTTER Group at individual stations and to demonstrate their manual skills.

As part of this construction rally, the classes worked together to produce benches for their schoolyard. We were now able to hand over these benches and wish the students many nice breaks on them!

Attention: you can do an internship at KUTTER and RIEBEL all over the year. Just find out more at www.kutter.de/karriere or www.riebel-bau.de/karriere .

LESS NEWS >